MRT Phase 2A to Have Four-Story Underground Station

The construction of the CP202 MRT Jakarta Phase 2A, which began on July 27, 2022, reached 6.82 percent until September 15, 2022.

These multi-story stations and tunnels are needed because Sawah Besar and Mangga Besar stations are built just under Jalan Gajah Mada (Sawah Besar Station) and Jalan Hayam Wuruk (Mangga Besar Station)

Several works are carried out at this stage such as the installation of Moveable Concrete Barriers (MCB) and fences as part of traffic engineering management, archeological test pit activities, and planting of affected trees.

Contract package 202 (CP202) is one of the segments of the MRT Jakarta Phase 2A construction work with the scope of work on the construction of Harmoni, Sawah Besar, and Mangga Besar stations. Including underground tunnels from Harmoni to Mangga Besar for a total of 1.8 kilometers (tunnels and stations).

MRT Jakarta Provides Public Information Center in Kota Tua Area

PT Jakarta Corporate Secretary Division Head, Rendi Alhial stated that the design of the CP202 tunnel and station is different from the CP201 and CP203 Phase 2A and 1. There are two main differences in the type of tunnel and underground station.

At Phase 1 and other Phase 2A stations, the underground station type consisted of two floors, while CP202 had four floors. Tunnel type CP202 is stacked, while Phase 1, as well as CP201 and CP203, are parallel.

"These multi-story stations and tunnels are needed because Sawah Besar and Mangga Besar stations are built just under Jalan Gajah Mada (Sawah Besar Station) and Jalan Hayam Wuruk (Mangga Besar Station)," he explained, Monday (10/3).

He explained that the four floors at the two stations will consist of the first floor as a concourse platform, the second floor as a platform for the tunnel to the south (Lebak Bulus Grab Station), the third floor as a concourse platform, and the fourth floor as a tunnel platform leading to the north (City Station).

Here are the Civil Profiles of the Three MRT Stations:

Harmoni Station

Consisting of two floors,  the station has a length of 252 meters, a width of 16.4 meters, and a depth of 17 meters below ground level. It has seven entrances, consisting of four on the sidewalk and three directly integrated with Transjakarta bus stop

Sawah Besar Station

Consisting of four floors, the station has a length of 200 meters, a width of 14.1 meters, and a depth of 27 meters below ground level. It has five entrances consisting of four on the sidewalk and one directly integrated with Transjakarta bus stop

Mangga Besar Station

Consisting of four floors, the station has a length of 220 meters, a width of 14.1 meters, and a depth of 28 meters below ground level. It has five entrances, including four on the sidewalk and one directly integrated with Transjakarta bus stop

Linked News
Popular News indeks
  1. Jakarta to Go Dark for One Hour on April 26, 2025

    access_time24-04-2025 remove_red_eye1224 personAldi Geri Lumban Tobing
  2. Pramono Wants to Strengthen Betawi Culture

    access_time26-04-2025 remove_red_eye330 personDessy Suciati
  3. Earth Day in Jakarta Reduces 297 Tons of Carbon Emissions

    access_time27-04-2025 remove_red_eye328 personBudhi Firmansyah Surapati
  4. Residents Advised to Apply for PPSU and Damkar Positions at Urban Village Offices

    access_time23-04-2025 remove_red_eye312 personFakhrizal Fakhri
  5. Earth Day, Pramono Encourages Citizens to Switch Off Lights Simultaneously

    access_time26-04-2025 remove_red_eye304 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik